General information, not legal advice. Laws change and your contract matters. Check the linked statutes and talk to an attorney about your situation.

This guide covers commercial subcontractors in North Carolina. It explains when you must be paid and how much retainage can be held, on public and private jobs. Every rule below links to the statute on the North Carolina General Assembly's website. Your contract can add terms, so read both.

Which law applies?

Public projects (G.S. 143-134.1)

When the GC must pay you

Retainage limits

When retainage comes back

Within 60 days after a pay request is submitted and either the owner receives a certificate of substantial completion or the owner gets beneficial occupancy or use (whichever the contract specifies), the retainage must be released (G.S. 143-134.1(b1)).

Private projects (Chapter 22C)

What to do with this