Guides

Lien waivers for subcontractors in North Carolina and South Carolina

Updated November 3, 2026.

General information, not legal advice. Laws change and your contract matters. Check the linked statutes and talk to an attorney about your situation.

A lien waiver is a document in which you give up some or all of your lien rights on a job, usually in exchange for a payment. Most general contractors ask for one with every pay application. This guide explains the usual kinds of waiver, what North Carolina and South Carolina statutes say about lien rights and notices, and what to check before you sign.

Each point is labelled so you know where it comes from:

Why GCs ask for lien waivers

The four common kinds of waiver

"Conditional", "unconditional", "partial" and "final" are industry terms. The North Carolina and South Carolina statutes linked on this page don't define them, so what a particular form does depends on its wording.

The rule of thumb most subcontractors follow (practice): sign conditional waivers to get paid, and unconditional waivers only for money that has already cleared your bank.

What North Carolina law says

You can't be made to give up lien rights to win the job

Lien agents and the Notice to Lien Agent

What South Carolina law says

This guide doesn't cover deadlines for filing or enforcing a lien. They're in the statutes linked above (G.S. 44A-12 in North Carolina and Title 29, Chapter 5 in South Carolina); ask a construction attorney how they apply to your job.

What to check before you sign a waiver

All of these are common practice, not law:

  1. The kind of waiver. Conditional or unconditional, partial or final. Don't sign an unconditional or final waiver when the form you expected was conditional or partial.
  2. The amount. It should match the payment this waiver covers: usually this pay app's amount due, not the contract total or the total billed to date.
  3. The through date. It should match the period your pay app covers, not a later date.
  4. Exceptions. If you're still owed money that this payment doesn't cover, such as retainage, pending or disputed change orders, extra work or an earlier unpaid pay app, list it as an exception if the form allows, or ask the GC to add it.
  5. Unconditional means paid. Sign an unconditional waiver only after the funds have cleared.
  6. Extra language. Some forms also release "all claims", confirm that your lower tiers are paid, or add indemnities. Those go beyond lien rights. Read them, and ask an attorney if you're unsure.
  7. The details. Project, owner, GC, your company name and the pay app number should all be right.
  8. Your own lower tiers. Collect your subs' and suppliers' waivers before the GC asks for them.
  9. Records. Keep a copy of every waiver with the matching pay app and payment record.

Every term on a waiver or pay app is explained in the pay application glossary.

Questions

Can a GC require me to waive my lien rights before I get the job in North Carolina?

Not enforceably. G.S. 44A-12(f) says an agreement to waive the right to file a claim of lien on real property, or to serve a notice of claim of lien upon funds, made in anticipation of and in consideration for the awarding of a contract is against public policy and unenforceable (G.S. 44A-12(f)). The same subsection doesn't prohibit subordination or release of a lien.

Is it safe to sign a conditional lien waiver before I'm paid?

Practice, not law: a conditional waiver is meant to take effect only when the stated payment is received, which is why GCs ask for it with the pay app. Check that the form's wording really makes it conditional, and that the amount and through date match the payment.

When should I sign an unconditional lien waiver?

Practice, not law: only for money that has already cleared your bank. An unconditional waiver usually takes effect when you sign it, whether or not you've been paid.

Do I need to send a Notice to Lien Agent in North Carolina?

On improvements that need a lien agent (costs of $40,000 or more, with an exception for an owner-occupied existing single-family home), a potential lien claimant may perfect a claim of lien on real property only if at least one statutory condition is met. One is that the lien agent received a Notice to Lien Agent from you no later than 15 days after you first furnished labor or materials (G.S. 44A-11.1; G.S. 44A-11.2(l)).

Who sends a notice of furnishing in South Carolina?

Sub-subcontractors and suppliers to a subcontractor, by certified or registered mail to the contractor. Without it, their liens are limited to what the contractor owes the subcontractor they supplied (S.C. Code § 29-5-20(B)).

Keep pay apps and waivers in step

PayClear builds each month's pay app from your schedule of values, so the amount and period on your waiver match what you billed. Try it free for 14 days.

Start your 14-day free trial

Sources

Check your next pay app before you send it

PayClear checks the math, retainage and change orders on your pay app so you can fix problems first. Try it free for 14 days.

Start your 14-day free trial